Successfully Lowered Rotor in the Bajina Bašta Reversible Hydropower Plant

The revitalization of the first unit of the Bajina Bašta reversible hydropower plant represents a crucial investment for “Elektroprivreda Srbije.” The project is in its final stages following the successful lowering of the 450-ton rotor into the generator stator.

This complex operation, lasting several hours, required precise work with cranes, hoists, and special cables, as well as an experienced team and favorable weather conditions.

“All conditions were met, and the task was completed flawlessly,” stated Slobodan Spasojević, head of the Mechanical Maintenance Department at the Bajina Bašta Hydropower Plant.

More:

The project is being executed by the Japanese company “Toshiba,” with support from subcontractors “Goša Montaža,” “Elektromontaža,” and “Elektroremont,” while oversight and crane operations are handled by the Bajina Bašta Hydropower Plant team, as stated in EPS’s announcement.

The next steps include connecting the rotor with the shaft, assembling the upper cross of the generator, and the upper guide bearing of the generator. The revitalization of the first unit is expected to be completed this year, with the second unit scheduled for 2025 as planned.

Upon completion of this revitalization project, taking place 42 years after the plant’s commissioning and 20 years since the last major overhaul in 2004, the long-term operation of this vital facility for “Elektroprivreda Srbije” will be secured. The revitalization ensures that the Bajina Bašta Hydropower Plant continues to provide reliable energy supply.

Energetski portal

READ MORE

komentari

FEATURED